Production hall

Hydro

/ purpose of the order
Renovation of a production hall including the roof of a polishing plant
/ hall area
10 000 m2
/ roof area of the polishing plant
4 200 m2
/ date of execution
2010
/ Scope of project work
  • dimension inventory of the existing steel structure, including surveys of the grade of structural steel used,
  • analysis of the load-bearing capacity of the existing halls,
  • design of reinforcement and installation technology of sprinkler system,
  • total area of halls: approx. 10 000 m2.
/ Polishing plant roof renovation
  • disassembly of lightning protection system,
  • disassembly of the gutter system,
  • disassembly of existing roof layers: PVC membrane, mineral wool, concrete screed, polystyrene,
  • delivery and installation of new roofing layers: 1.5mm thick PVC membrane, 15cm thick mineral wool, vapour barrier,
  • delivery and installation of a new lightning protection system,
  • delivery and installation of a guttering system,
  • delivery and installation of necessary flashings,
  • sealing of skylights and roof penetrations,
  • supply and installation of a belay system.